Link road build - update on the development so far

31/7/13- Progress on the Bexhill to Hastings Link Road.  Remains of the railway bridge at Woodsgate Park31/7/13- Progress on the Bexhill to Hastings Link Road.  Remains of the railway bridge at Woodsgate Park
31/7/13- Progress on the Bexhill to Hastings Link Road. Remains of the railway bridge at Woodsgate Park
There’s already been dramatic change in Sidley and Crowhurst as work on the new road progresses.

East Sussex County Council says work this month has included -

- Great Crested Newt and Reptile trapping and relocation

- Archaeological investigation throughout the site

31/7/13- Progress on the Bexhill to Hastings Link Road.  Looking North East towards Queensway31/7/13- Progress on the Bexhill to Hastings Link Road.  Looking North East towards Queensway
31/7/13- Progress on the Bexhill to Hastings Link Road. Looking North East towards Queensway

- Construction of the haul route to provide access for construction traffic

Hide Ad
Hide Ad

- Ground treatment works – these provide a base for the earthworks

- Demolition of the properties on London Road

- Demolition of the Woodsgate Park Bridge leaving a section of the west abuttment and wing walls to form part of the new bridge

- Root removal works from earlier site clearance – this can only be done now that dormice are out of hibernation

- Diversions of services including Crowhurst Road (completed 6 weeks ahead of schedule) and coordinated to include highways patching works

Hide Ad
Hide Ad

- Unexploded ordinates surveys – this is to survey the land for possible unexploded bombs left from WWII

- Completion of the site compound in Crowhurst – now main office site Fencing works – this includes fencing protected areas of trees and habitat.